Journal of Nuclear Fuel Cycle and Waste Technology Vol.18 No.2(E) pp.247-260
DOI : https://doi.org/10.7733/jnfcwt.2020.18.2(E).247

Decommissioning Cost Estimation of Kori Unit 1 Using a Multi-Regression Analysis Model

Han Young Joo, Jae Wook Kim, So Yun Jeong, Joo Hyun Moon*
Dankook University, 119, Dandae-ro, Dongnam-gu, Cheonan-si, Chungcheongnam-do, Republic of Korea
Corresponding Author. Joo Hyun Moon, Dankook University, E-mail: jhmoon86@dankook.ac.kr, Tel: +82-41-550-3513
February 3, 2020 ; April 8, 2020 ; August 11, 2020

Abstract


A multi-regression model was developed to estimate the decommissioning cost for Kori unit 1 using foreign nuclear power plant (NPP) decommissioning cost data. First, the decommissioning cost data were collected for 13 boiling water reactors and 16 pressurized water reactors and converted into the values as of November 2019. Then, for the regression model, the decommissioning cost was chosen as the dependent variable, and two variables were selected as independent variables: a contamination factor that was designed to reflect the operational characteristics of the decommissioned NPP and the decommissioning period. A statistical package in the R language was used to derive the regression model. Finally, the regression model was applied to estimate the decommissioning cost for Kori unit 1. The estimated decommissioning cost for Kori unit 1 was 663.40~928.32 million US dollars (782,812~1,095,418 million Korean won).



회귀 분석 모델을 이용한 고리 1호기 해체 비용 추정

주 한영, 김 재욱, 정 소윤, 문 주현*
단국대학교, 충청남도 천안시 동남구 단대로 119

초록


본 논문에서는 고리 1호기 해체 비용 추정을 위해 외국 원자력발전소 해체 비용 데이터를 현가화한 후 원자력발전소 해체 비 용 추정 회귀 분석모델을 개발하였다. 이 모델 개발에 사용된 데이터는 해체 또는 진행 중인 BWR 13기, PWR 16기의 해체 비용 데이터이다. 회귀 분석모델 도출을 위해, 해체 비용을 종속변수로 정하고, 해체 원전의 운전 특성을 반영할 수 있게 고 안된 Contamination factor와 해체 기간을 독립변수로 선정하였다. 빅데이터 분석 도구인 R language의 통계패키지를 이용 하여 회귀 분석모델을 도출하였다. 이 회귀 분석 모델을 적용하여 고리 1호기 해체 비용을 예측한 결과, 미화 663.40~928.32 백만 달러, 한화 약 7,828.12억~1조 954.18억 원이 소요될 것으로 예측되었다.



    National Research Foundation of Korea
    NRF-2017M2B2A9A02049319
    NRF-2020M2D2A2062436

    1. 서론

    “해체”는 원자력안전법에 따라 허가 또는 지정을 받은 시 설의 운영을 영구적으로 정지한 후, 해당 시설과 부지를 철 거하거나 방사성오염을 제거함으로써 원자력안전법 적용대 상에서 배제하기 위한 모든 활동을 말한다[1]. 원자력발전소 영구정지 사유로는 경제성 저하, 정치적 판단, 중대사고 등 이 있으며, 일반적으로 원전 노후화에 따른 경제성 상실이 가장 큰 이유다.

    Fig. 1은 현재 전 세계에서 운영 중인 원자력발전소를 가 동 연수에 따라 구분된 것이다. IAEA PRIS에 따르면, 2019년 12월 현재 449기가 운영 중이며, 운영 중인 원자력발전소 가 운데 30년 이상 장기 운전 중인 원자력발전소는 278기, 40년 이상은 72기이며, 50년 이상은 5기이다[2].

    JNFCWT-18-2(E)-247_F1.gif
    Fig. 1

    Number of Reactors in Operation by Age.

    우리나라는 40년간 운전한 고리 1호기를 해체하기 위해 영구정지 상태로 전환하였으며, 해체 계획이 승인되고 사용 후핵연료 반출이 완료되는 대로 해체를 추진할 것으로 보인 다. 이 이외에도 30년 이상 운전된 가압 경수로(PWR)와 가 압중수로(PHWR)의 설계수명이 연장되지 않을 경우, 2029 년까지 총 12기의 원자력발전소 해체가 추진될 것으로 예 상된다.

    원자력발전소 해체는 해체 작업 수행과 자원관리를 병 행한다. 해체 비용 추산을 위해서는 일반적으로 WBS (Work Breakdown Structure) 및 ISDC를 이용해 만들어진 해체 비용 평가 프로그램을 이용하여 평가한다[3]. 미국은 해체 비용 코드 로 CECP (PNL), DECAS (AVZ), DECCER (TRG), CAT (RSCS) 등을 개발하였다. 일본 JAERI는 JPDR 해체 경험을 기반으로 COSMARD을 개발하였다. 슬로바키아 SLOVAK ELECTRIC는 OMEGA를, 영국 UKAEA는 PRICE를 개발하였다[4].

    신뢰성 있는 해체 비용을 추산하기 위해서는 여러 가지 구체적 데이터가 다수 필요하다. 하지만 해체를 결정한 시점 이나 초기 진행단계에서는 데이터 부족으로 정확한 해체 비 용 추산이 어렵다. 전 세계적으로 원자로 특성, 즉, 출력, 운 영기간, 규제 기준 등이 상이하여, 해체 비용을 정확히 예측하 기 쉽지 않다. 하지만 각국은 해체 비용 충당 근거를 마련하 기 위해, 원자력발전소 특성에 기반하여 해체 비용을 추산하 고 있다. 프랑스는 전세계 원자력발전소 호기당 평균 해체 비 용을 6,546억원으로 추정하였다[5]. 우리나라는 원자력발전 소 해체 비용 충당금을 매 2년마다 검토하여 고시하고 있는 데, 최근 고시한 2019년 기준 해체 비용은 8,129억원이다. 이 는 2017년 고시한 7,515억원 대비 8.1% 인상된 금액이다[6].

    본 논문에서는 최근 우리 정부가 고시한 원자력발전소 해체 비용이 고리1호기 해체하는데 충분한지를 확인하고자, 전 세계 해체 완료 또는 진행 중인 원자력발전소 해체 비용 데이터를 현가화하고 통계분석 프로그램 R을 이용해 회귀 분 석하여 해체 비용 추산 모델을 개발하였다.

    2. Analysis Method and Procedure

    2.1 Nuclear Power Plant Data

    IAEA PRIS에 개시 기준으로 2019년 12월 현재 영구 정 지된 원전은 Fig. 2에서 보듯이, 전 세계 20개 국가에 총 178 기이다. 미국이 37기로 가장 많으며 영국과 독일이 그 뒤를 따르고 있다. 하지만 노형에 따라 해체 소요 기간과 전략이 차이가 난다. 특히 영국이 다수 보유한 가스 냉각로(Gas Cooled Reactor)는 감속재로 사용된 흑연 방사화로 인해 즉 시 해체 대신 지연 해체 전략을 적용하고 있어, 실제 해체까 지는 장시간이 걸릴 것으로 예상된다. Fig. 34는 PRIS의 데이터 중 현재 운전 중 및 영구 정지된 원자로 수를 노형별 로 정리한 것이다. 가압경수로와 비등경수로가 다수를 차지 하고 있음을 알 수 있다.

    JNFCWT-18-2(E)-247_F2.gif
    Fig. 2

    Number of Nuclear Reactors in Permanent Shutdown by Country.

    JNFCWT-18-2(E)-247_F3.gif
    Fig. 3

    Number of Nuclear Reactors in Operation by Reactor Type.

    JNFCWT-18-2(E)-247_F4.gif
    Fig. 4

    Number of Nuclear Reactors in Permanent Shutdown by Reactor Type.

    Table 1은 PRIS에 12월 현재 전 세계적으로 해체 완료 또 는 예정된 원전 중 해체 비용이 산출된 원전들의 소유 국가, 원자로형, 상업운전 개시일 및 영구정지일과 출력을 정리한 것이다. 이 중 Sweden의 Oskarshamn 1,2, 미국의 Oyster Creek, Vermont Yankee, Indian Point 3 등은 해체가 진행 또는 계획 중으로 해당 금액은 추산 금액이다.

    Table 1

    Summary of Nuclear Reactors on Decommissioning or Decommissioned in the World

    Country Name Reactor type Commercial Operation date Permanent Shutdown date Thermal Power (MWt) Electric Power (MWe) Gross Capacity (MWe)

    United State Big Rock Point BWR 1963.03.29 1997.08.29 240 72 71
    Fort St. Vrain HTGR 1979.07.01 1989.08.29 842 330 342
    Haddam Neck PWR 1968.01.01 1996.12.05 1,825 582 603
    Maine Yankee PWR 1972.12.28 1997.08.01 2,630 825 900
    Milestone BWR 1971.03.01 1998.07.01 2,011 660 684
    Rancho Seco PWR 1975.04.17 1989.06.07 2,772 918 917
    Trojan PWR 1976.05.20 1992.11.09 3,411 1,130 1,155
    Three Mile PWR 1974.09.02 2019.09.20 2,568 819 880
    Island 1
    Yankee Rowe PWR 1961.07.01 1991.10.01 600 175 180
    San Onofre 1 PWR 1968.01.01 1992.11.30 1,347 436 456
    Oyster Creek BWR 1969.12.01 2018.09.17 1,930 650 652
    Vermont Yankee BWR 1972.11.30 2014.12.29 1,912 514 635
    Zion 1 PWR 1973.12.31 1998.02.13 3,250 1,040 1,085
    Zion 2 PWR 1974.09.17 1998.02.13 3,250 1,040 1,085
    Shoreham BWR 1986.08.01 1989.05.01 2,436 809 849
    Humboldt Bay BWR 1963.08.01 1976.07.02 220 65 65
    Pilgrim BWR 1972.12.01 2019.05.31 2028 655 711
    Crystal river 3 PWR 1977.03.13 2013.02.05 2568 825 890
    Fort Calhoun 1 PWR 1973.09.26 2016.10.24 1500 478 512
    Kewaunee PWR 1974.06.16 2013.05.07 1772 535 595
    United State Indian Point 1 PWR 1962.10.01 1974.10.31 615 265 277
    Indian Point 2 PWR 1974.08.01 2020.04.30 3216 873 1067
    Indian Point 3 PWR 1976.08.30 2021.04.30* 3216 965 1085
    Germany Niederaichbach HWGCR 1973.01.01 1974.07.31 321 100 106
    Wuergassen BWR 1975.11.11 1994.08.26 1,912 640 670
    Spain Jose Cabrera 1 PWR 1969.08.13 2006.04.30 510 153 150
    (Zorita)
    Santa Maria BWR 1971.05.11 2013.07.06 1,381 440 466
    de Garona (Long term shutdown)
    2017.08.02
    (Permanent shutdown)
    Japan Tokai 1 GCR 1966.07.25 1998.03.31 587 159 166
    Tsuruga 1 BWR 1970.03.14 2015.04.27 1,070 341 357
    Mihama 1 PWR 1970.11.28 2015.04.27 1,031 320 340
    Genkai 1 PWR 1975.10.15 2015.04.27 1,650 529 559
    Ikata 1 PWR 1977.09.30 2016.05.10 1,650 538 566
    Shimane 1 BWR 1974.03.29 2015.04.30 1,380 439 460
    Lithuania Ignalina1 LWGR 1985.05.01 2004.12.31 4,800 1,500 1,300
    Ignalina2 LWGR 1987.12.01 2009.12.31 4,800 1,500 1,300
    Sweden Oskarshamn1 BWR 1972.02.06 2017.06.19 1,375 440 492
    Oskarshamn2 BWR 1975.01.01 2016.12.22 1,800 580 661
    Switzerland Muehleberg BWR 1972.11.06 2019.12.20 1,097 306 390
    Netherlands Dodewaard BWR 1969.03.26 1997.03.26 183 54 60
    Italy Enrico Fermi PWR 1965.01.01 1990.07.01 870 247 270
    (Trino)
    Caorso BWR 1981.12.01 1990.07.01 2,651 840 882
    Garigliano BWR 1964.06.01 1982.03.01 506 150 160

    Table 1에서 보면, 42기의 원자력발전소가 해체가 진행 중이거나 완료되었으며, 이 중 BWR과 PWR은 각각 17, 20기 이다. 본 논문에서는 이 중 BWR 13기, PWR 16기에 대한 해 체 비용 데이터를 활용하였다.

    2.2 Method

    원자력발전소 해체 비용은 WBS, ISDC 또는 각국이 개발 한 프로그램을 이용하여 산출할 수 있다. 본 논문에서는 기존 방법과 달리 해체 비용 데이터를 회귀 분석하여 해체 비용 산정 회귀 분석모델을 개발하였다. 일반적으로 SPSS, SAS, SYSTAT, R, MATLAB 등을 데이터 통계 분석에 이용한다. 이 중 R은 빅데이터 분석 도구이자, 통계 계산과 시각화에 특화 된 프로그래밍 언어이다. 본 논문에서는 R의 통계 패키지를 이용하여 통계분석을 수행하였다.

    본 논문은 원자력발전소 해체 비용과 원자력발전소 해체 관련 변수 사이에 어떤 관계가 있는지를 확인하기 위해 회귀 분 석을 적용했다. 회귀 분석은 변수 사이의 관계를 파악한다는 부분에서는 상관 분석과 유사하지만, 상관 분석이 두 변수 사 이의 관계 정도만을 나타내지만 회귀 분석은 독립변수와 종 속변수 사이의 인과관계를 수학적인 함수식으로 표현하여, 독립변수에 원하는 값을 대입하여 종속변수의 값을 추정할 수 있게 해준다[7].

    회귀 분석은 종속변수에 영향을 주는 독립변수의 수에 따라 단일 회귀 분석과 다중회귀 분석으로 나눌 수 있으며, 회귀 분석모형은 아래의 식 (1)과 같이 표현할 수 있다[8,9].

    Y = β 0 + β 1 X 1 + β 2 X 2 + + β p X p + ε, ε N ( 0 , σ 2 )
    (1)

    이 때, 식은 Y = β 0 + β 1 X 1 + β 2 X 2 + + β i X i 에 해당하는 함수와, ε에 해당하는 확률적 오차로 구분된다. 즉, 회귀 분 석모형은 데이터를 통해 얻어지는 함수 부분과 오차 부분이 결합된 형태이다. 이 회귀 분석모형을 바탕으로 다중선형회 귀식을 추정하기 위해, p개의 설명 변수를 고려한 다중 선형 회귀 분석모형은 다음 식 (2)와 같다.

    E ( Y i ) = β 0 + β 1 X 1 i + β 2 X 2 i + + β p X p i , i = 1 , , n
    (2)

    이때, E(Yi)는 Yi 의 기대값이면서 회귀식으로 표현할 수 있으며 추정값은 다음과 같은 식 (3) 형태로 표현할 수 있다.

    y ^ i = b 0 + b 1 X 1 i + b 2 X 2 i + + b p X p i , i = 1 , , n
    (3)

    여기서 b 0 , b 1 , b 2 , , b p 는 설명변수의 계수인 β 0 , β 1 , β 2 , , β p 의 추정값이며, 최소제곱추정법으로 추정할 수 있다. 최소 제곱추정법은 β 0 , β 1 , β 2 , , β p 의 추정값인 b 0 , b 1 , b 2 , , b p i = 1 n i 2 가 최소화되도록 β0를 선택하는 방법으로 β0j번 째 설명변수 xj를 제외한 나머지 설명변수( X 1 , X j 1 , X j + 1 , X p )들이 고정되어 있다고 가정하였을 때, Xj가 1단위 변화할 때 종속변수 Y의 변화량이다.

    이렇게 추정된 다중선형회귀식은 유의성 검정을 위하여 오차제곱합 SSE (Sum of Squares due to Error)을 사용하는 데, 이는 다음 식 (4)와 같이 표현할 수 있다.

    SSE = i = 1 n ( y i y ^ i ) 2 = i = 1 n ( y i b 0 b 1 x 1 i b 2 x 2 i b p x p i ) 2
    (4)

    최종적으로 설명변수들이 반응변수를 선형적으로 얼마나 잘 반영하고 있는지 표현하는 결정계수(Coefficient of determination, R2)는 다음 식 (5)와 같이 정의한다.

    R 2 = S S R S S T = 1 S S E S S T = i = 1 n ( y ^ i y ¯ ) 2 i = 1 n ( y ^ i y ¯ ) 2
    (5)

    이 때, SSR ( i = 1 n u ^ i 2 ) 은 residual sum of squares, 즉 잔차 의 제곱의 합으로 회귀식으로 설명이 되지 않는 변동의 합을 의미한다. SST ( i = 1 n ( y i y ¯ ) 2 ) 는 total sum of squares, 즉, Y 의 편차의 제곱으로 전체 변동의 합이다. SSE ( i = 1 n ( y ^ i y ¯ ) 2 ) 은 회귀식으로 추정한 Y의 편차 제곱의 합으로, 회귀 분석 모형으로 설명이 가능한 부분이다. R2의 범위는 0‹R2‹1 이 며, 1에 가까울수록 추정된 회귀 분석모형이 총변동량의 많 은 부분을 설명할 수 있음을 의미한다. 하지만 R2는 독립변 수 수가 증가할수록 커지는데, 종속변수의 변동을 반영하지 못하는 변수가 추가되더라도 결정계수의 값이 증가할 수 있 기 때문에 이러한 문제를 보정하고자 고려되는 것이 수정 결 정계수(Adjusted coefficient of determination, Adjusted R2) 으로 표본의 크기와 독립변수의 수를 고려하여 다음 식 (6) 과 같이 표현할 수 있다.

    Adjusted R 2 = 1 n 1 ( n p 1 ) ( 1 R 2 )
    (6)

    이 때, np – 1은 자유도로 n은 표본의 수이며, p는 독 립변수의 수이다.

    본 논문에서는 PWR과 BWR 해체 비용을 종속변수(Y) 로, 원자력발전소 해체 비용에 영향을 주는 운전 특성 변수 를 독립변수(X)로 두어 회귀식을 도출하였다. 이 때, 회귀 분 석모형으로 계산된 해체 비용 적합도를 평가하기 위해 R2, Adjusted R2과 Root mean square error (RMSE)를 활용하 였다. 동시에 통계적 유의성을 확인하기 위해 가설에 대한 p-value 값 확인, t 검정, 분산팽창요인(Variance Inflation factor, VIF)를 활용하였다.

    영가설(H0)에 대한 검증을 위해서는 p-value의 값에 따 라, H0에 대한 기각 여부를 결정할 수 있다. 이때 신뢰구간 을 구하기 위해서는 다음의 가정을 따른다. 모수를 Ө로 하 는 밀도함수 f(x:Ө)인 모집단으로부터 크기가 n인 확률표본 을 x1, x2, ⋯ xn이라고 할 때, 주어진 유의수준 값 0‹α‹1에 대해 신뢰하한 Θ L = ϕ ^ L 과 신뢰상한 Θ H = ϕ ^ H P ( θ L ^ < θ < θ H ^ ) = 1 α 를 만족하고, ӨL‹ӨH일 때, 구간 [ӨL, ӨH]는 모수 Ө에 대한 (1 – α)100% 신뢰구간이라고 하며, 1 – α를 신뢰수준이 라고 한다. 이때 구하고자 하는 데이터들의 분포가 정규분포 를 따른다면, 신뢰구간은 다음 식 (7)과 같이 표현할 수 있다.

    P = ( Z α 2 < X ¯ μ σ n < Z α 2 ) = 1 α
    (7)

    여기서 X 는 표본의 평균, σ는 분산, α는 유의수준을 의 미한다

    t 검정(t-test)는 데이터 분석에서 기본적으로 수행되는 평 균분석으로 두 데이터 세트에서 평균과의 유의미한 차이가 존재하는지 분석하는 것으로 다음 식 (8)을 통해 구할 수 있다.

    t = d ¯ d 0 s d n
    (8)

    이 때, d 는 관측값 차이의 평균, d0는 각 데이터 세트 사 이의 평균차, n은 해당 데이터 세트의 표본수를 의미한다.

    그리고 회귀 분석모형의 적합성 판단에 분산팽창요인 (Variance inflation factor, VIF)을 사용할 수도 있다. 회귀 분석모형에 사용되는 독립 변수간 상관 관계를 가지는 것 을 다중공선성(Multicollinearity)이라 하는데, 이때 다중공 선성을 가질 경우 부정확한 회귀결과를 갖게 된다. 이를 확인하기 위해 VIF를 사용하며, 다음 식 (9)을 통해 계산 할 수 있다.

    VIF i = 1 1 R i 2
    (9)

    다중 회귀 분석 Y = X 1 + X 2 + + X p 을 할 때 i번째 독립 변수에 대한 다중 회귀 분석 X 1 X 1 + + X i 1 + X i + 1 + X p 의 중회귀계수를 R j 2 라 한다. i번째 독립변수에 대한 VIFi 가 1인 경우 변수 간의 관련이 없으며, 10 이상인 경우 변수 사이의 다중공선성을 가질 가능성이 높다고 볼 수 있다[10].

    2.3 Consideration of Independent variable (Xi)

    회귀 분석모형 도출을 위해, 종속변수(Y)를 해체 비용으 로, 독립변수(Xi)를 BWR과 PWR 해체 비용에 영향을 미칠 것 으로 예상하는 원자력발전소 특성으로 선정하였다. 특히, 원 자력발전소 해체 비용 중 큰 비중을 차지하는 폐기물 비용과 노동비용을 반영할 수 있는 인자를 고려하였다.

    폐기물 비용은 원자력발전소 오염 정도에 따라 증가하 고, 이는 원자력발전소 가동 기간에 비례하여 증가할 것이 다. 이러한 원전의 운전특성을 반영하면서, 회귀 분석모형 에 사용될 수 있도록 식 (10)과 같은 형태의 변수를 도입 하였다.

    Contamination factor = Operation period × ln(MWt) × Operation factor/100
    (10)

    이 때, Operation factor는 국제원자력기구 PRIS에서 제공 하는 값으로 총 가동가능 시간 중 실제 가동한 시간 비율이다.

    원자력발전소 해체기간 중에도 부지 및 시설 관리비용, 작업자 인건비 등이 발생하므로, 해체기간이 해체 비용에 영 향을 줄 것이다. 해체 완료된 원자력발전소는 실제 해체 기 간을 변수로 선정하였으며, 계획 중인 원전의 경우 추진 중 인 해체 기간을 변수로 선정하였다.

    최종적으로 회귀 분석 모형은 종속변수(Y)를 해체 비 용으로 선정하였으며, 독립변수(Xi)는 운전특성을 반영한 Contamination factor와 해체기간으로 구성하였다. 아울 러 회귀 분석 모형에 대한 H0은 원자력발전소 해체 비용 은 운전기간, 열출력, Operation factor을 반영해 계산한 Contamination factor와 해체 기간이 연관성이 없는 것 으로 설정하였다. H1은 원자력발전소 해체 비용은 Contamination factor 및 해체기간과 연관이 있는 것으로 설 정하였다.

    3. Results and Discussion

    해체가 진행 또는 완료된 BWR 13기를 Table 2에, PWR 16기를 Table 3에 정리하였다. 해체 비용의 경우 해체 비용 산정 시점이 상이하여 현재 가치를 직접 비교하기 어렵기 때 문에, 미국 노동통계국(Bureau of Labor Statistics)에서 제공 하는 소비자 물가지수(Consumer price index)를 이용하여 현재 가치(2019.11 기준)로 환산하였다[11].

    Table 2

    Summary of BWR under Decommissioning or Decommissioned [13-19]

    Cumulative values not calculated when more than 50% of required data is missing in PRIS. Then its value assumes at 70%.

    Country Name Operating period [Year] Thermal capacity [MWt] Operation factor [%] Contamination factor Decommissioning period [Year] Cost [M US $] Present value [M US $] *Nov, 2019

    United State Big Rock Point 34 240 73.0 136.03 9 420 455.17
    [13]
    Milestone 1 27 2011 69.2 142.12 60 422 457.33
    [14]
    Oyster Creek 48 1930 78.2 283.97 18 627 668.19
    [14]
    Vermont Yankee 42 1912 86.3 273.87 15 561 597.85
    [14]
    Humboldt bay 13 220 NC* 49.08 12 727 828.24
    [15]
    Pilgrim 47 2028 76.0 272.00 60 1661 1695.34
    [16]
    Netherlands Dodewaard 28 183 86.0 125.44 8 133 185.41
    [17]
    Italy Caorso 8 2651 43.5 27.43 32 480 669.16
    [17]
    Garigliano 17 506 44.8 47.42 27 263 366.64
    [17]
    Spain Santa Maria de 42 1381 81.6 247.81 16 308 340.08
    Garona
    [18]
    Switzerland Muhleberg 47 1097 90.4 297.43 15 178 249.50
    [17]
    Oskarshamn1 45 1375 65.0 213.236 10 114 125.87
    [19]
    Oskarshamn2 42 1800 75.8 238.64 10 137 151.27
    [19]

    Average 33.9 1333.4 72.29 181.11 22.5 463.9 522.3
    Table 3

    Summary of PWR under Decommissioning or Decommissioned [20-24]

    Cumulative values not calculated when more than 50% of required data is missing in PRIS. Then its value assumes at 70%.

    Country Name Operating period [Year] Thermal capacity [MWt] Operation factor [%] Contamination factor Decommissioning period [Year] Cost [M US $] Present value [M US $] *Nov, 2019

    United State Haddam Neck 28 1825 76.0 159.79 10 819 872.80
    [14]
    Maine Yankee 24 2630 73.0 137.96 8 592 641.57
    [13]
    Rancho Seco 14 2772 46.4 51.05 20 466 504.02
    [13]
    Three Mile 45 2568 76.7 272.03 62 1228 1255.43
    Island 1
    [20]
    Trojan 16 3411 57.9 75.49 13 429 600.04
    [13]
    Yankee Rowe 30 600 77.4 147.76 15 608 658.91
    [13]
    Zion 1 24 3250 63.9 124.21 10 500 540.80
    [13]
    Zion 2 24 3250 65.9 128.09 10 500 540.80
    [13]
    San Onofre 1 24 1347 55.1 95.11 32 622 674.08
    [13]
    Crystal river 3 36 2568 66.9 189.36 56 895.9 945.16
    [21]
    Fort Calhoun 1 43 1500 77.3 242.14 48 1213 1240.30
    [22]
    Kewaunee 39 1772 85.1 247.96 62 919 11084.60
    [23]
    Indian Point 1 12 615 NC* 53.94 10 598 598.0
    [24]
    Indian Point 2 46 3216 77.1 286.41 11 701 701.82
    [24]
    Indian Point 3 45 3216 73.7 267.83 12 1002 1002.38
    [24]
    Spain Jose Cabrera 1 36 510 78.9 177.30 11 341 358.3
    (Zorita)

    Average 30.4 2190.6 70.08 166.03 24.4 714.7 763.74

    운영 기간은 해당 원전의 상업운전 일자와 영구정지 일 자를 기준으로 운영정비 기간에 대한 고려 없이 전체 기간 만을 고려하였다. 해체과정 중 방사성 오염 사건·사고 발생 여부는 실제 해체 비용에 영향을 주는 인자이지만, 본 논문에 서는 해당 인자에 대한 고려는 제외하였다.

    Table 2에서 보듯이, 해체가 완료 또는 진행 중인 BWR 로서 해체 비용이 확정 또는 추산이 완료된 원자력발전소는 전 세계 6개국 13기으로, 평균 33.9년 운전되었으며, 평균 522.3 백만달러의 해체 비용이 발생하였다.

    Table 3은 영구정지 중인 PWR에 대한 것으로서, 미국과 스페인의 원자로 16기가 해체 완료 또는 진행 중에 있다. 스 페인은 Jose Cabrera (Zorita) 원전을 해체하고 있다. 대부분 원전이 20년 이상 운전하였으며, 해체 비용은 763.7 백만 달 러가 발생하였다.

    Table 2,3 중 Humboldt Bay와 Indian Point unit 1의 Operation factor는 PRIS에서 제공하지 않아 70%로 가정하 였다.

    3.1 Application of Regression Analysis to Decommissioning Cost Data

    3.1.1 Analysis for BWR Decommissioning Cost Data

    BWR에 대한 회귀 분석 결과는 Table 45에 정리해 놓 았다. Fig. 5에서 실제 비용과 본 논문에서 추정한 값 사이의 차이를 확인할 수 있다. 본 논문에서 BWR 해체 비용 추정에 사용된 회귀 분석모형은 다음 식 (11)과 같다.

    Cost = 113.608 + 0.389 × Contamination factor + 15.196 × Decommissioning period
    (11)

    Table 4

    Multi-regression Analysis Results for BWR Data

    Coefficient (βi) Std. error t value p-value VIF

    (Constant) 113.608 246.028 0.462 0.654 -
    Contamination factor 0.389 1.016 0.383 0.710 1.002
    Decommissioning period 15.196 5.621 2.703 0.022 1.002
    Table 5

    Statistic Test Results for BWR Data

    R2 Adjusted R2 RMSE MAE Std. Error

    0.4248 0.3097 302.3423 247.3839 344.7233
    JNFCWT-18-2(E)-247_F5.gif
    Fig. 5

    Comparison of the real decommissioning costs and the predicted costs for BWR.

    해체 비용은 Contamination factor, 해체(예상)기간에 대 한 βi 는 양의 값의 가지고 있었으나, BWR 회귀식에 대한 R2 = 0.4248, p-value는 0.063으로 이 회귀식으로 설명할 수 있는 부분이 적고, p‹0.05으로 귀무가설 H0을 기각할 수 없 다. 따라서 대안가설 H1을 채택할 수밖에 없으므로, 식 (11) 은 BWR 해체 비용 추정 회귀식으로 부적합하다. 또한 변수 중 Contamination factor의 p-value는 0.05 이상으로 적합한 변수로서 판단할 수 없다.

    3.1.2 Analysis for PWR Decommissioning Cost Data

    PWR에 대한 다중 회귀 분석 결과는 Table 67에 정리 하였다. Fig. 6에서 실제 비용과 본 논문에서 추정한 값 사이 의 차이를 확인할 수 있다. 본 논문에서 PWR 해체 비용 추정 에 사용된 회귀식은 다음 식 (12)와 같이 구할 수 있다.

    Cost = 329.853 + 1.533 × Contamination factor + 7.347 × Decommissioning period
    (12)

    Table 6

    Multi-regression Analysis Results for PWR Data

    Coefficient (βi) Std. error t value p-value VIF

    (Constant) 329.853 89.876 3.67 0.003 -
    Contamination factor 1.533 0.55 2.786 0.015 1.264
    Decommissioning period 7.347 2.104 3.492 0.004 1.264
    Table 7

    Statistic Test Results for PWR Data

    R2 Adjusted R2 RMSE MAE Std. Error

    0.7372 0.6968 134.2286 106.3934 148.9133
    JNFCWT-18-2(E)-247_F6.gif
    Fig. 6

    Comparison of the real decommissioning costs and the predicted costs for PWR.

    PWR에 대한 회귀식에 대한 R2 = 0.7372, Adjusted R2 = 0.6968이다. 해당 회귀식의 적합도를 확인하기 위한 p-value는 0.0001이며, 회귀식의 각 변수의 p-value 역시 0.05 보 다 작아 PWR은 해당 회귀모델에 대한 H0을 기각 후 H1을 채 택할 수 있다. 즉, 식 (12)를 PWR 해체 비용 추정 회귀 분석 모형으로 사용 가능하다.

    3.2 Analysis for Sensitivity of regression model

    민감도 분석은 모형을 이용한 현상 해석과 예측 결과에 대한 불확실성을 정량적으로 판단하기 위한 방법이다. 합리 적 모형 구축이나 신뢰성 있는 시나리오 분석을 위해서는 모 형의 매개변수나 입력 데이터 특성에 따른 모형의 민감도를 분석할 필요가 있다. 이를 위한 방법으로 Monte Carlo 분석, LH-OAT (Latin-hypercube one factor at a time) 분석 방법 등이 있다. 본 논문에서는 LH-OAT를 이용해 민감도 분석을 수행하여, 독립변수의 해체 비용에 대한 영향을 평가하였다. 회귀 분석모형이 부적합한 것으로 판명된 BWR에 대한 회귀 분석모형에 대해서는 민감도 분석을 수행하지 않았다. PWR 에 회귀 분석모형에 대한 민감도 분석 결과는 Table 8에 정리 하였다. PWR의 해체 비용을 영향을 미치는 2가지 변수인 해 체 기간과 Contamination factor에 대한 민감도는 거의 유사 한 것으로 확인되었다.

    Table 8

    Sensitivity Analysis results for PWR

    Ranking No. Parameter Name Relative Importance Fraction [%]

    1 Decommissioning period 22.3062 52.18
    2 Contamination factor 20.4424 47.82

    3.3 Application of Regression Model to Kori 1

    현재 영구정지 상태인 고리 1호기는 PWR이므로, 본 논 문에서 도출된 PWR 회귀분석모형을 적용해 해체 비용을 추 산할 수 있다. Table 9에는 회귀식에서 사용된 인자와 해체 비용 추산금액을 정리하였다.

    Table 9

    Variables for cost Estimation of Kori 1 decommissioning by the Regression Model

    Operating period [Year] Thermal Power (MWt) Operation factor Contamination factor Estimated Decommission period Cost [M US $]

    39.194 1729 79.5% 232.30 15 795.86

    그리고 R 패키지 중 [Predict]를 이용하여 고리 1호기 해 체 비용 구간을 추산하였다. 회귀변수 중 해체 기간을 15년 으로 고정하지 않고 0~30년까지 변화시켜가며 고리 1호기 해체 비용 범위를 추산하였다. 해체 기간에 따른 고리 1호기 해체 비용을 회귀 분석 모형에 대하여 95% 신뢰구간을 적용 하여 하한과 상한값, 평균을 구해 Fig. 7과 같이 표시하였다.

    JNFCWT-18-2(E)-247_F7.gif
    Fig. 7

    95% confidence intervals of estimated decommissioning cost for Kori 1 with change in decommissioning period.

    고리 1호기에 대한 해체 기간을 15년으로 했을 때, 해체 비 용 기대값(평균)은 약 795.86 백만 US 달러, 한화로 9,391.14 억원(1$ = 1,180원, 2020년 1월 29일 기준)이며, 95% 신뢰구 간은 663.40 백만 US 달러(7,828.12억원)~928.32 백만 US 달러(1조 954.18억원)로 추산되었다.

    4. Conclusions

    이 논문에서는 R을 이용해 BWR과 PWR 해체 비용 데이 터를 회귀 분석하여 해체 비용 추정 회귀 분석 모형을 개발하 였다. 원자력발전소 운영 기간, 열출력, Operation factor를 결합한 Contamination factor와 해체기간을 독립변수로 선 정하여 다중 회귀 분석 모형을 도출하였다. PWR에 대해 산 출된 회귀 분석모형은 해체 비용 추정모형으로 적합했으나, BWR에 대해 산출된 회귀 분석 모형은 추정모형으로서 적합 하지 않다. 이 논문에서 도출된 PWR 회귀 분석 모형을 PWR 인 고리 1호기에 적용하여 추산한 해체 비용 기대값(해체기 간 15년 가정)은 9,391.14억 원으로, 2019년 고시된 호기 당 해체 비용(8,129억 원) 대비 15.5% 많았다.

    해체 비용 예측 회귀 분석모형의 정확도를 높이기 위해 서는 회귀 분석모형에 적합한 회귀 변수 개발과 실제 해체 비용 데이터의 지속적 축적이 필요하다. 본 논문에서 제시 된 BWR 해체 비용 회귀 분석 모형의 신뢰성을 높이기 위해 서는 회귀 분석 모형에 적용 가능한 회귀 변수 도출이 필요 하며, 35기 BWR 운영 또는 해체를 계획 중인 일본 등의 실 제 해체 비용 데이터를 확보하여 이를 회귀 분석 모형에 반 영할 필요가 있다.

    Acknowledgements

    This work was supported by the National Research Foundation of Korea grant NRF-2017M2B2A9A02049319 and NRF-2020M2D2A2062436 funded by the Korean Government.

    Figures

    Tables

    References

    1. Nuclear Safety and Security Commission (NSSC), Nuclear Safety Act (2020).
    2. IAEA, Dec. 23 2019. PRIS - World Statics. Accessed Dec. 23 2020. Available from: https://pris.iaea.org/ PRIS/WorldStatistics/OperationalReactorsByCountry. aspx.
    3. D.B. Monteiro, J.M. Moreira, and J.R. Maiorino, “A new management tool and mathematical model for decommissioning cost estimation of multiple reactors site”, Prog. Nucl. Energy, 114, 61-83 (2019).
    4. C.R. Kim, T.H. Sung, S.Y. Yoon, and S.Y. Kim. Development of regulation technology for decommissioning and decontamination of nuclear power plants, Nuclear Safety and Security Commission, 38-41, TRKO201800042525 (2018).
    5. Cour des Comptes, The costs of the nuclear power sector, Cour des Comptes - Thematic public report, 84-115 (2012).
    6. Ministry of Trade, Industry and Energy, Regulation on Estimation of Management Cost of Radioactive Waste and Management Share of Spent Fuel, MOTIE Notice No. 2019-217 (2019).
    7. J.H. Kim, Environmental Statistics & Data Analysis, 205-269, Hannarae, Seoul (2018).
    8. S.H. Kang, Introductory statistic, 456-494, Free academy, Paju (2012).
    9. H.G Kang, Statistical methods for health care research, 6th ed., 315-344, Koonja, Paju (2017).
    10. D.M. Levine, Statistics for managers using Microsoft Excel, 5th ed., 613-644, Pearson Prentice Hall, New Jersey (2008).
    11. U.S. Bureau of Labor Statistics, Nov. 30 2019. US BLS – Inflation and Price Accessed Jan. 30 2020. Available from: https://data.bls.gov/cgi-bin/cpicalc.pl ?cost1=33929&year1=198205&year2=201911.
    12. International Atomic Energy Agency, Release of sites from regulatory control on termination of practice, IAEA Safety Guide, IAEA Safety Standards WS-G- 5.1 (2006).
    13. Organization for Economic Cooperation and Development Nuclear Energy Agency, The practice of cost estimation for decommissioning of nuclear facilities, OECD/NEA report, 59-60, NEA No. 7237 (2015).
    14. Organization for Economic Cooperation and Development Nuclear Energy Agency, Costs of decommissioning nuclear power plants, OECD/NEA report, 59-77, NEA No. 7201 (2016).
    15. Pacific Gas and Electric Company, Humboldt Bay Nuclear Power Station Post-Shutdown Decommissioning Activities Report, Rev. 0, 4-5 (2018).
    16. Energy Nuclear Operation, Pilgrim Nuclear Power Station Post-Shutdown Decommissioning Activities Report, Rev. 4, 1-7 (2013).
    17. Organization for Economic Cooperation and Development Nuclear Energy Agency, Decommissioning nuclear power plants: Policies, strategies and Costs, OECD/NEA report, 53-65, NEA No. 3590 (2003).
    18. K. Kim and R. McGrath, “Factors Impacting Decommissioning Costs”, Proc. of the Waste Management 2013 Conference, WM-13576, February 24-28, 2013, Phoenix, Arizona.
    19. H. Larsson, Å. Anunti, and M. Edelborg, Decommissioning Study of Oskarshamn NPP, Svensk Kärnbränslehantering AB Report, SKB R-13-04 (2013).
    20. Exelon Generation Company, Decommissioning Cost Analysis Report, Rev, 0, 19-23 (2019).
    21. Duke Energy Florida LLC, Crystal River Unit 3 Nuclear Generating Plant Site Specific Decommissioning Cost Estimate, Rev. 0, Sec 6 4-5 (2018).
    22. Omaha Public Power District, 2019 Annual Decommissioning Funding/Irradiated Fuel management Status Report, 2-3 (2018).
    23. Dominion Energy Kewaunee, Kewaunee Power Station Post-Shutdown Decommissioning Activities Report, No. 13-064, 30-31 (2013).
    24. Holtec Decommissioning International, Indian Point Energy Center Indian Point Units 1,2 and 3 Post-Shutdown Decommissioning Activities Report, Rev. 0, 17- 18 (2019).