Journal of Nuclear Fuel Cycle and Waste Technology Vol.17 No.1 pp.95-106
DOI : https://doi.org/10.7733/jnfcwt.2019.17.1.95

Suggestion of Risk Assessment Methodology for Decommissioning of Nuclear Power Plant

ByeongIk Park,JuYoul Kim,Chang-Lak Kim*
KEPCO International Nuclear Graduate School, 658-91, Haemaji-ro, Seosaeng-myeon, Ulju-gun, Ulsan, Republic of Korea
*Corresponding Author. Chang-Lak Kim, KEPCO International Nuclear Graduate School, E-mail: clkim@kings.ac.kr, Tel: +82-52-712-7333

Abstract

The decommissioning of nuclear power plants should be prepared by quantitative and qualitative risk assessment. Radiological and nonradiological hazards arising during decommissioning activities must be assessed to ensure the safety of decommissioning workers and the public. Decommissioning experiences by U.S. operators have mainly focused on deterministic risk assessment, which is standardized by the U.S. Nuclear Regulatory commission (NRC) and focuses only on the consequences of risk. However, the International Atomic Energy Agency (IAEA) has suggested an alternative to the deterministic approach, called the risk matrix technique. The risk matrix technique considers both the consequence and likelihood of risk. In this study, decommissioning stages, processes, and activities are organized under a work breakdown structure. Potential accidents in the decommissioning process of NPPs are analyzed using the composite risk matrix to assess both radiological and non-radiological hazards. The levels of risk for all potential accidents considered by U.S. NPP operators who have performed decommissioning were estimated based on their consequences and likelihood of events.

원자력발전소 해체 위험도 평가 방법론 개발

박병익,김주열,김창락*
한국전력국제원자력대학원대학교, 울산광역시 울주군 서생면 해맞이로 658-91

초록

원전 해체를 준비함에 있어 정성적 또는 정량적 위험도 평가는 필수요소이다. 해체 공정간 발생하는 방사선학적 및 비방사선학적 위험요소는 해체 작업자 및 대중의 안전을 보장하기 위해 사전에 평가되어야 한다. 현재 해체 경험이 많은 미국의 기 존 사업자들 및 NRC의 경우 위험의 중대성만 평가하는 결정론적 위험도 평가에 집중하고 있다. 하지만 최근 IAEA는 위험도 매트릭스를 활용한 위험도평가를 결정론적 위험도 평가의 대체안으로 제안하고 있다. 따라서 본 연구에서는 위험도평가에 앞서 해체 공정 별 해체 활동을 Risk Breakdown Structure에 맞추어 정리하였고, 미국 20여개 해체 원전에서 해체 공정별 위험도 평가 시행 중 선정한 해체 활동간 잠재적 사고를 해체 활동에 맞게 체계적으로 정리하였다. 그리고 복합 리스크 매트릭 스를 개발 및 활용하여 해체 공정간 방사선학적 및 비방사선학적 위험요소의 위험도를 평가하여 정량적으로 수치화 하였다.